ID
|
Description
|
Target Date
|
Status
|
Dependencies/Notes
|
0.0
|
Infrastructure and Decisions
|
0.1
|
Basic project hosting available
on opensolaris.org
|
Dec 2005
|
COMPLETE
|
|
0.2
|
Distributed SCM evaluation/choice
|
4/5/06
|
COMPLETE
|
Mercurial chosen
|
0.3
|
Email to community re: choice
|
4/7/06
|
COMPLETE
|
|
|
1.0
|
Subversion (SVN) Milestones
|
|
1.1
|
SVN Beta: SCM web app available for beta testing
by CCD and JDS.
|
6/16/06
|
COMPLETE
|
Website/UI
support. Moved from 6/12/06.
|
1.2
|
SVN Beta: Test respositories
set up for Companion CD and JDS.
|
6/27/06
|
COMPLETE
|
Date moved from 6/5 (CCD) and
6/12 (JDS).
|
1.3
|
SVN Beta: Start beta testing
with Companion CD and JDS.
|
7/20/06
|
COMPLETE
|
Initial functionality available
to manage and use SVN code respositories. Date moved from 6/5
(CCD) and 6/12 (JDS) due to problems encountered with the set-up of
site hosting machines.
|
1.4
|
SVN Beta 2: JDS Test
repository available
|
8/28/06
|
COMPLETE
|
|
1.5
|
SVN Beta 2: CCD Test repository
available
|
9/7/06
|
COMPLETE
|
|
1.6
|
SVN Beta Concludes
|
10/6/06
|
COMPLETE
|
|
|
1.6
|
Full SVN Support available to all projects on
opensolaris.org
|
10/11/06
|
COMPLETE
|
|
|
2.0
|
Mercurial (hg) Milestones
|
|
2.1
|
Necessary updates to Mercurial complete
|
December 2006
|
GREEN
|
Support for rename functionality. Work on
new Mercurial release that contains this functionality is in progress.
|
|
2.2
|
Mercurial bundles for ON consolidation published
|
5/26/06
|
COMPLETE
|
Downloadable build-to-build Mercurial change
information.
|
2.3
|
hg Beta starts on
opensolaris.org/ON mirror available
|
10/18/06
|
COMPLETE
|
|
|
2.4
|
hg Beta concludes
|
12/20/06
|
|
Moved two weeks because dependent on Mercurial
release.
|
|
3.0
|
Consolidation Milestones
|
|
3.1
|
JDS Consolidation live repository available on
opensolaris.org
|
10/19/06 |
COMPLETE
|
|
3.2
|
Companion
CD Project live
repository available on
opensolaris.org
|
10/31/06 |
COMPLETE
|
|
|
3.3
|
Sun-internal transition: ON Consolidation gate
using Mercurial
|
02/09/07
|
|
Moved two weeks because dependent on 2.1 above
(rename
functionality).
|
|
3.4
|
ON Consolidation live repository available on
opensolaris.org
|
04/13/07
|
|
Moved two weeks because dependent on 3.3 (ON
internal transition) and 2.4
(website support).
|
|
4.0
|
Project Milestones
|
|
4.1
|
SVN integrated into SFW Consolidation
|
December 2006
|
GREEN
|
Have ARC approval. Working through code
review input.
|
|
4.2
|
Mercurial integrated into SFW Consolidation
|
July 2006
|
COMPLETE
|
Build 46
|